April 9 – April 22, 2017

  • Continue Roofing.
  • Complete Waterproofing Exterior Sheathing, all sides.
  • Continue Parging Foundation walls.
  • Continue installing exterior Windows & Doors, all sides.
  • Continue installing the finished Soffits.
  • Start installing the Dryvit Stucco system.
  • Start installing the Nichiha Wall Panel system.
  • Continue Mechanical, Sprinkler, Plumbing & Electrical Roughing throughout building.
  • Continue Low Voltage Roughing throughout building.
  • Continue Underground Utilities.
  • Start Elevator installation.
  • Deliveries will occur nearly every day.
  • Exterior operations are weather contingent.
  • No Holidays.

 

GDC is fully committed to Equal Housing Opportunity and we fully comply with the Federal Fair Housing Act. We do not discriminate against any person because of race, color, religion, sex, disability, familial status, or national origin. All applications are judged on the same standards; Income Verification, Rental History, Credit History and a Criminal Background Check, one person or family at a time, on a first come first serve basis.